Plan Outlay 2008 - 2009
S.No.
Head
Plan outlay 2008-09 (Proposed) 
(Rs. In Crores)
1. Generation (Shared Generating Projects)  
1.1 S&I Preliminary Exps for Chambal Development Plan Phase-II  1.00  
1.2 Renovation & Modernisation/Up rating of shared Generating Stations  
   (a) Up rating of Gangwal and KPS of BBMB 9.00  
   (b) Other capital works by BBMB

 Total (1)

10.00  

2.

Transmission
2.1 Ongoing + New Woks 815.00  
2.2 EAP works/world Bank Loan  -  
2.3 Counterpart for II  -  
  Total (2) 815.00  
  Grand Total (1+2)  825.00  
     
 
 