S. NO. NAME OF TH E SECTION NO. OF CIRCUITS TOTAL LENGTH (CIRCUIT KILOMETER) YEAR OF COMPLETION / ENERGISATION  
1 Hissar-Rajgarh S/C 72.000 1959-60  
2 Rajgarh-Ratangarh S/C 98.800 1960-61  
3 GandhiSagar-Kota D/C 149.860 1960-61  
4 Sakatpura-Ind.Area Kota D/C 22.680 July,1962  
5 Kota-Lakheri D/C 140.460 July,1962  
6 Lakheri-SwaiMadhopur D/C 83.680 July,1962  
7 SwaiMadhopur-Jaipur via Niwai S/C 128.740 July,1962  
8 Jaipur-Phulera S/C 56.320 April,1963  
9 Phulera-Ajmer S/C 71.310 April,1963  
10 Neemuch-Debari S/C 117.870 June,1963  
11 Ratangarh-Jaipur S/C 206.500 March,1965  
12 Jodhpur-Pali S/C 60.150 August,1967  
13 Jaipur-Alwar S/C 127.600 February,1968  
14 Inter Connection RPS D/C 38.400 February,1968  
15 T-off from Gandhi Sagar-Kota line to RAPP S/C 3.700 1968-69  
16 R.P.S.-Bhilwara D/C 230.400 March,1969  
17 Alwar-Bharatpur S/C 112.000 March,1969  
18 Bhilwara-Pali S/C 137.600 April,1969  
19 Ajmer-Beawar S/C 50.000 August,1969  
20 Bhilwara-Beawar S/C 96.000 September,1970  
21 Sirsa-Hanumangarh S/C 82.000 December,1970  
22 Debari-Zawar mines S/C 36.000 September,1972  
23 Hanumangarh-Rajiasar S/C 95.000 9/6/1973  
24 Kota-Jawahar Sagar D/C 46.000 17/8/73  
25 Ratangarh-Bikaner S/C 126.000 11.4.73  
26 Mathura-Bharatpur S/C 3.500 18.7.73  
27 Debari-Sirohi S/C 117.000 8.10.74  
28 Kota-Sangod S/C 61.000 21.1.76  
29 R.P.S.-Ind.Area Kota S/C 42.000 12.8.75  
30 Alwar-Hindaun S/C 103.010 20.1.76  
31 Beawar-Bilara S/C 64.500 16.1.76  
32 Sirohi-Bhinmal S/C 61.500 25.3.76  
33 Alwar GSS-MIA Alwar D/C 20.200 May,1976  
34 Debari-Kankroli S/C 53.000 June,1976  
35 Churu-Jhunjhunu S/C 50.000 24.9.76  
36 Sirohi-Jalore S/C 61.000 21.11.76  
37 Beawar-Gulabpura S/C 40.000 22.12.76  
38 Zawarmines-Sagwara S/C 84.650 2.1.77  
39 Zawarmines-Sagwara S/C 6.550 31.7.97  
40 Bikaner-Bazzu S/C 92.000 March,1977  
41 Phulera-Makrana S/C 64.000 March,1977  
42 Debari GSS-Zinc Smelter S/C 1.360 1976-77  
43 Jodhpur-Bilara S/C 73.610 14.10.77  
44 Jodhpur-Dechu S/C 106.500 23/26.1.78  
45 Dechu-Pokran S/C 48.920 26.1.78  
46 Kunda ki Dhani-Dausa S/C 53.250 22.2.78  
47 Sagwara-Banswara S/C 44.300 23.3.78  
48 Alwar-KishangarhBas S/C 35.000 31.3.78  
49 Jalore-Balotra S/C 74.250 October,1978  
50 Ratangarh-Deedwana Via Sujangargh  GSS S/C 80.970 30.3.79  
51 Alwar-Kotputli S/C 62.000 31.3.79  
52 Nimbahera-Chittorgarh S/C 37.000 31.3.79  
53 V.K.I.A.-M/S PratapSteel
S/C 1.060 1978-79  
54 I.A.Kota-J.K. S/C 0.570 1978-79  
55 I.A.Kota-S.F.C. S/C 0.840 1978-79  
56 Beawar-Merta S/C 70.690 4.11.79  
57 Kota-Bundi S//C 33.670 31.3.80  
58 Chittor-Birla Cement Works S/C 1.500 7.6.80  
59 Kota-Modak
S/C 57.700 3.10.80  
60 Heerapura-Renwal
S/C 45.000 24.1.81  
61 Debari GSS-Udaipur Cement Works
S/C 8.160 14.1.81  
62 Suratgarh-Padampur
S/C 48.980 3.2.81  
63 Hindaun-Dholpur
S/C 88.400 2.7.81  
64 Nimbahera GSS -J.K.Cement Works
S/C 4.000 30.7.81  
65 Bhilwara-Chittorgarh S/C 48.600 30.7.83  
66 Ratangarh-Rajiasar
S/C 143.000 30.7.83  
67 T-off Rajgarh
S/C 3.000 1.10.81  
68 T-off Purana Ghat
D/C 6.800 2.10.81  
69 Modak-Jhalawar
S/C 25.120 15.10.81  
70 Sangod-Baran
S/C 27.480 28.11.81  
71 Palana-Mavli
D/C 19.380 16.11.81  
72 Mavli-Dariba
S/C 23.800 23.1.82  
73 Nimbahera-Pratapgarh
S/C 68.300 19.12.81  
74 Dariba GSS-Hindustan-Zink Ltd.
S/C 3.000 15.1.82  
75 Jhunjhunu-Chirawa S/C 27.400 15.1.82  
76 T-off Sanganer S/C 0.000 28.1.82/Dismentaled  
77 Sirohi-Pindwara
S/C 24.300 15.2.82  
78 Kishangarh Bas-Bhiwadi
S/C 45.600 8.2.82  
79 Bilara-Sojat
S/C 35.000 21.2.82  
80 Pindwara-Basantgarh
S/C 13.000 1.2.82  
81 Heerapura-Sanganer-Purana Ghat
S/C 33.220 5.10.82  
82 Kotputli-Shahpura
S/C 38.890 26.2.83  
83 Alwar S/S 132 KV-M/S Modi Alkalies S/C 5.720 9.2.83  
84 Alwar S/S 132 KV-M/S Modi Alkalies D/C 7.660 9.2.83  
85 Sawai Madhopur-Tonk
S/C 58.000 26.3.83  
86 Bharatpur 220 KV &132 Interconnection D/C 13.000 30.10.82  
87 I.A.Kota-M/S Shri Ram Vinayal &  Chemical,KOTA S/C 0.930 19.3.83  
88 Sujangarh-Nagaur S/C 101.000 25.1.83  
89 Sirohi-Sumerpur S/C 47.210 25.1.83  
90 Balotra-Barmer
S/C 84.690 31.3.83  
91 Padampur-Sriganganagar S/C 43.000 15.5.83  
92 T-off Nagar
D/C 5.600 30.10.83  
93 Kotputli-Behror
S/C 29.750 14.1.84  
94 Sikar-Nawalgarh
S/C 30.660 30.4.83  
95 Kotputli-Neem ka Thana
S/C 44.950 29.10.83  
96 Bharatpur-Nadbai
D/C 65.000 28.10.83  
97 Nadbai-Weir
S/C 27.600 28.10.83  
98 Weir-Hindaun
S/C 36.500 28.10.83  
99 Bundi-Kekri
S/C 84.300 30.10.83  
100 Gotan-Bhopalgarh
S/C 24.500 28.3/84  
101 Merta-Gotan S/C
32.770 28.3.84  
102 Hindaun-Gangapurcity
S/C 45.960 23.12.83  
103 Nadbai-Alwar
S/C 64.450 22.6.80  
104 Makrana-Kuchaman
S/C 17.330 28.8.84  
105 Bilara-Borunda
S/C 31.160 19.11.84  
106 Hirapura-Bagru
S/C 20.150 31.12.84  
107 Dausa-Bandikui
S/C 36.218 21.1.85,31.7.92  
108 Bandikui-Mandawar
S/C 29.500 26.1.85  
109 Pindwara-Abu Road
S/C 47.600 31.1.85  
110 RAPP Link Line
S/C 3.220 23.1.85  
111 Beawar-Shree Cemant
S/C 5.800 16.2.85  
112 Gotan-JK white cement
S/C 2.120 March,85  
113 Mahi Power House I-'132KV GSS  Lodha,Banswara D/C 27.200 Dec.84  
114 Modak-Bhawanimandi
S/C 36.180 31.3.86  
115 Renwal-Danta
S/C 27.340 10.10.85  
116 Sumerpur-Falna
S/C 16.670 11.1.86  
117 HindaunGSS-Rly.Traction D/C 3.000 31.3.86  
118 GangapurGSS-Rly.Traction D/C 4.420 31.3.86  
119 Bharatpur-Rly.Traction D/C 2.800 19.3.86  
120 Madri T-Off D/C 4.400 3.3.86  
121 Bhilwara-Gangapur S/C 40.330 17.10.86  
122 LILO Bhinder D/C 20.400 4.3.87  
123 Banswara-Pratapgarh S/C 67.560 10.2.87  
124 P.H.2 - Banswara S/C 28.180 1986-87  
125 Chittorgarh-Chittorgarh Cement Works S/C 1.790 1986-87  
126 Sikar-Dhod S/C 22.160 29.3.87  
127 Gotan-Kharia Khangar(Indian Rayon & Ind.) S/C 5.930 29.3.87  
128 Chirawa-Pilani S/C 16.600 30.3.88  
129 SawaiMaddhopur-SawaiMadhopur Rly.Feeder D/C
3.180 23.9.87  
130 Kishangarh-Malpura S/C 63.610 31.12.87  
131 Kota-Gurla Rly.Station D/C 24.580 21.8.87  
132  Lakheri-Lakheri Rly. Station D/C 1.960 24.9.87  
133  Modak-RamganjMandi D/C 16.500 21.11.87  
134  Jhalawar-Prithvipura(J.K.Feeder) D/C 17.640 11.3.89  
135  Mahi P.H.2 - Banswara
D/C 58.690 20.12.88  
136  Ajmer-Bherunda
S/C 37.940 8.11.88  
137  V.K.I.A.Jaipur loopline
D/C 8.140 88-89  
138  Purana Ghat-JawaharNagar
D/C 7.500 7.11.88  
139  Puranaghat-Dausaline TO Bassi Loopline
D/C 2.330 24.9.88  
140  Khetri-Chirawa
D/C 54.040 30.9.88  
141  Khetri-Neem Ka Thana
S/C 52.460 26.8.89  
142  Sagawara-Dungarpur
S/C 46.900 30.9.88  
143  SVCI First-Kota Feeder
D/C 1.600 5.9.89  
144  Debari-Mavli
S/C 24.150 30.3.90  
145  Bhinmal-Raniwara
S/C 26.370 2.5.89  
146  Gotan-Nihon Nirman S/C
1.070 19.11.89  
147  Dechu-PS-5 S/C
51.000 2.5.89  
148  PS5-PS4
S/C 21.580 2.5.89  
149  P.S.-4-P.S.-3(Upto Bhimji Ka Gaon)
S/C 11.770 2.5.89  
150  Chittor-Chanderia
S/C 8.420 8/1/1991  
151 LILO  Sikar-Ratangarh For132K.V. Laxmangarh (SIKAR) D/C 2.300 11/12/1990  
152  Khetri-Gudagorji
S/C 40.900 11/4/1990  
153 Rajgarh-Bhadra
S/C 59.190 15/6/90  
154   Madri-RSMM
S/C 12.800 19/3/91  
155  Gulabpura-Agucha
S/C 11.210 11/1/1991  
156  Jodhpur-Baori-Bhopalgarh
S/C 81.000 2/5/1991  
157  Sirohi-Reodar
S/C 42.000 25/7/91  
158  Sangod-Kawai
S/C 49.480 30/3/92  
159  Bhinmal-Sanchore S/C
59.000 31/10/91  
160  LILO Jodhpur-Bhopalgarh For Baori D/C
5.800 5/12/1991  
161  Weir-Bayana D/C 36.620 29/3/92  
162  Suratgarh-Anoopgarh
S/C 72.220 30/3/92  
163  LILO-Mangaliyas TO Nasirabad
D/C 50.000 7/9/1991  
164  Nasirabad-Kekri S/C 48.000 17/6/91  
165  Interconnection 132 GSS Jodhpur-220  K.V.GSS Jodhpur
D/C 9. 060 91-92  
166  Chirawa TO Sultana
S/C 14.830 19/11/92  
167 Pokaran -Jaisalmer
S/C 105.315 27/8/92  
168   LILO Heerapura-Chambal at NPH Jaipur
D/C 13.040 94-95'97-98  
169  Khetri -Bhuwana S/C
15.150 29/9/92  
170  Merta -Kuchera
S/C 35.494 31/12/92  
171  LILO Nagaur-Merta For Kuchera
D/C 5.322 30/3/93s  
172  Dausa-Lalsot
S/C 34.904 25.12.92  
173 LILO Debari Sirohi At Sukher D/C 9.176 8.1.93  
174  LILO Suratgarh-Hanumangarh For Pilibanga

D/C 2.200 25.1.93  
175  LILO Heerapura -Renwal At Hingonia
D/C 9.732 23.1.93  
176  LILO Bhilwara Pali At Kharchi
D/C 3.764 23.1.93  
177  Sangod-Jhalawar
S/C 43.980 31.3.93  
178  Jaisalmer - Ramgarh
D/C 3.492 31.3.93  
179  Jaisalmer - Ramgarh S/C 62.626 31.3.93  
180  Pali- Falna

S/C 72.571 31.3.93  
181  Nalla Power House GSS -Chambal GSS
S/C 0.000 29.8.92 Realignment  
182  PS 5 - PS 6
S/C 17.702 13/6/92  
183 PS 7 - Tinwari
S/C 13.469 1992-93  
184   PS 8 - Jodhpur
S/C 23.178 1992-93  
185 Sumerpur-Umaidpur
S/C 23.537 28.2.93  
186   LILO Beawar Bilara For S/S at Jaitaran
D/C 11.300 10/11/1993  
187  Nagaur -Kuchera
S/C 35.320 15/2/94  
188  Anoopgarh-Gharsana
S/C 23.730 31.3.94  
189  LILO Heerapura-Bagru For S/S At Bhankrota
D/C 3.740 31.3.94  
190  Sikar-Udaipurwati
S/C 36.060 19.3.94  
191  Bharatpur-Deeg-Kama
S/C 53.080 30.3.94  
192  Bilara-Peepalia Kalan
S/C 26.410 31.3.94  
193  Jhalawar -Eklera
S/C 51.040 31.3.94  
194  Reengus -SriMadhopur Bhim ji ka Gaon
S/C 7.912 31.12.93  
195  PS 2 - PS 3
S/C 12.900 12.6.93  
196  PS 1 - PS 2
S/C 9.740 12.6.93  
197  PS 9 - PS 1
S/C 9.930 12.6.93  
198  Behror-Shahjhanpur S/C
19.786 1.6.94  
199  Behror-Shahjhanpur
D/C 3.280 1.6.94  
200  LILO Ajmer-Nasirabad For Saradhna
D/C 1.960 29.3.95  
201 LILO Jodhpur-Tinwari For Banar
S/C 3.500 31.3.95  
202  LILO-Pindwara-Sirohi-Debari Line For Laxmi  Cement Works
D/C 11.060 29.10.94  
203  Jaisalmer-Ramgarh II
S/C 64.510 13.3.95  
204  Sangod-Anta
S/C 25.060 28.3.95  
205  LILO GS-RPS for Baroli
S/C 1.010 30.3.95  
206  Bazzu -PS I
S/C 57.940 30.3.95  
207  Bazzu -PS I
S/C 0.395 95-96  
208  LILO Hanumangarh-Sirsa For Amarapuratheri
S/C 4.830 31.3.95  
209  LILO Alwar-Kotputli For Bansur Sub Station
D/C 0.600 30.3.95  
210  Chittorgarh-Grasim Cement
S/C 20.250 94-95  
211  Hindaun-Karauli
S/C 31.500 17.6.93  
212  LILO-220 kv GSS 'Merta to 132 kv  Kuchera Nagaur line
D/C 1.440 16.12.95  
213  LILO Jodhpur-Tinwari for Banar
D/C 4.800 31.3.96  
214  LILOJodhpur-Tinwari for CHB -Jodhpur
D/C 0.380 30.3.96  
215  PS 8 - PS 1
S/C 7.260 30.4.95  
216  Jaisalmer -Barmer
D/C 8.780 31.3.96  
217  Jaisalmer -Barmer
S/C 150.250 31.3.96  
218  DLF Cement works( Jaitaran -Village RAS)
S/C 19.610 10.6.95  
219  Sakatpura -Gopal mill
S/C 14.540 30.3.96/31.3.97  
220  Reengus to Danta Ramgarh
S/C 40.060 25.11.95  
221  LILO- Heerapura-Chambal For 132 KV GSS Mansarowar
D/C 0.000 31.3.96-Realignment  
222  Weir-Bayana
S/C 18.000 29.3.96  
223  Hindaun-SriMahaveerji
S/C 13.290 10.11.95  
224  Hindaun-SriMahaveerji
D/C 1.540 10.11.95  
225  LILO Bhilwara-Chittorgarh For Hamirgarh D/C 14.000 10.11.95  
226  LILO -Banswara-Debari For Salumber

D/C 20.000 5.1.96  
227  Bali-Falna
D/C 20.100 31.3.96  
228  LILO -Ratangarh-Suratgarh For Sardarsahar
D/C 0.960 2/1/1996  
229  LILO Ratangarh-Bikaner for Dungargarh
D/C 0.320 30.3.96  
230 Sriganganagar-Lalgarh
S/C 13.480 9/1995  
231   LILO Sirsa-Hanumangarh for Amarapura Theri
D/C 4.840 30.6.95 2nd Ckt.Com.  
232  LILO-VKIA-Chomu For 132 KV GSS (Rampura dabri)
D/C 0.950 31.3.97  
233  Nagaur-Khinvsar
S/C 40.410 16.12.96  
234  Jodhpur -Tinwari
S/C 60.050 9.11.96  
235  220 KV GSS Jodhpur-M/S Murless steel
S/C 4.730 20.11.96  
236 Pindwara-Binani cement
S/C 7.230 9.2.97  
237   LILO -Bikaner-Gajner For PUGAL ROAD-Bikaner
D/C 12.830 18.1.97s  
238  Bikaner-Gajner
D/C 5.280 24.8.97  
239  Bikaner-Gajner
S/C 46.220 24.8.97  
240  Bikaner-Gajner
S/C -6.856 2000-2001  
241  Suratgarh-Nokhasar
S/C 68.810 31.3.97  
242 Sri Ganganagar RICCO VIHAR S/C 4.300 30.3.97  
243   LILO-Chittorgarh-Nimbahera For Sawa (Chittorgarg J.K.)

D/C 7.000 31.3.97  
244  LILO- Phulera- Makarana For Nawa
D/C 4.300 31.3.97  
245  Bhinmal -Dhorimanna
S/C 94.275 31.3.97  
246 Bhinmal- Sayla
S/C 45.590 31.3.97  
247  LILO-132 KV Heerapura Phulera line for  132KV GSS Sirsi D/C 5.200 17.5.96  
248   Bhiwadi-Kushkhera

S/C 10.800 30.3.98  
249 Tinwari-Denchu
S/C 62.520 31.3.98  
250   Lakheri-A.C.C.
S/C 1.080 28.2.98  
251  Gopal Mill IA,Kota
S/C 14.380 30.6.97  
252 Bhawani Mandi-Dug
S/C 58.490 26.3.98  
253 Bali-Rani
S/C 23.380 31.3.98  
254  Kankroli-Amet
S/C 30.980 31.3.98  
255  LILO-Bhilwara-Asind For Rayla
D/C 29.220 31.3.98  
256  Nimbhahera-Sawa
S/C 19.020 31.1.98  
257  Dungarpur-Rishabhdev
S/C 28.250 31.3.98  
258  Hanumangarh-Sangariya
S/C 16.470 31.3.98  
259 Hanumangarh-Sangariya D/C 10.340 31.3.98  
260   Suratgarh-Jokhasar
D/C 44.060 14.12.97  
261  Bikaner-Nokha
S/C 57.410 31.3.98  
262  LILO Newai -Sanganer For 132 KV GSS  Chaksu D/C 3.640 30.3.99  
263 LILO Ajmer -Bherunda Line For MDSU

D/C 0.100 11.10.98  
264   LILO Jodhpur -Tinwari Line For 132 KV GSS  Mathania
D/C 1.300 30.3.99  
265  Barmer-Gadara
S/C 81.100 24.2.99  
266  Barmer-Gadara
D/C 8.800 24.2.99  
267  Abu Road-Reodar
S/C 44.880 27.3.99  
268  Madri -Sukher
S/C 12.270 11.11.98  
269  Rayla -Shahpura
S/C 31.630 31.1.99  
270  Banswara -R.S.M.Ltd.
S/C 0.600 Exiting  
271  Bharatpur-Deeg-Kanma
S/C 0.840 98-99  
272  Sanganer -Mansarover
D/C 8.780 II circuit 15.9.99  
273  Chirawa - Surajgarh
S/C 9.000 31.5.99  
274  Chirawa - Surajgarh
D/C 0.820 31.5.99  
275  LILO Sirohi-Jalore FOR Bagra GSS
D/C 3.560 29.3.2000  
276  Danta- Chitava
S/C 20.920 10.1.2000  
277  Kuchaman-CHITAVA
S/C 18.330 17.3.2000  
278  LILO FOR MANDORE GSS
D/C 0.200 30.3.2000  
279  JODHPUR-TINWARI LINE FOR SURSAGAR GSS
D/C 5.480 18.6.99  
280  LILO JALORE-BALOTRA LINE For SIWANA  GSS
D/C 7.640 31.10.99  
281 LILO-Sukher-Gogunda For SISARMA D/C 23.920 8.3.2000  
282  BIKANER- NAPASAR
S/C 20.050 27.5.99  
283  SUJANGARH-BIDASAR
S/C 25.060 30.8.99  
284  MORAK GSS TO MANGALAM CEMENT
S/C 0.400 99-2000  
285  V.K.I.A- KUKAS
S/C 16.860 99-2000  
286  KUKAS-KUNDA KI DHANI (I CIRCUIT)
S/C 3.610 99-2000  
287  KUKAS-KUNDA KI DHANI (II CIRCUIT)
S/C 3.750 99-2000  
288  KUKAS-JAMUA RAMGARH
S/C 14.170 99-2000  
289  Dahra - Chambal Fertilizers
S/C 16.168 13.05.2000  
290  LILO Debari-Kankroli For Nathdwara
D/C 16.236 03.06.2000  
291  I/C 220 kv Dahra - Goapl Mill I/A
D/C 24.130 30.06.2000  
292  Diversion Work of HZL line
S/C 2.797 30.08.2000  
293  I/C 220 kV & 132 kV GSS Jhunjhunu
D/C 21.660 28.09.2000  
294  Bikaner-Loonkaransar S/C
58.234 31.10.2000  
295  Bikaner-Loonkaransar
D/C 13.712 31.10.2000  
296  Kuchaman - Molasar
S/C 22.299 30.11.2000  
297  K. G. Bas - Mundawar Via Kherthal
S/C 20.065 30.11.2000  
298  Mandalgarh - Began
S/C 22.485 07.12.2000  
299  LILO Reengus-Sikar For Ranoli
D/C 3.366 19.01.2001  
300  LILO Bhilwara-Mandalgarh For Suwana
D/C 2.972 19.01.2001  
301  Mansarowar - SMS Stadium
D/C 11.492 13.02.2001  
302  Baran - Kelwara
S/C 46.548 28.02.2001  
303  LILO Heerapura-VKIA for Vaishali Nagar D/C
2.952 30.03.2001  
304 Rayala -Gulabpura S/C
33.291 30.03.2001  
305   LILO Sanganer-Purana Ghat For SITAPURA
D/C 0.072 21.04.2001  
306  I/C 220 KV TO 132 KV GSS BHIWADI
S/C 4.960 30.04.2001  
307  LILO -Nagaur-Sujangarh For LADNOO D/C
7.096 15.06.2001  
308  CHOMU-MARKHI S/C
25.624 16.06.2001  
309 BHADRA-NOHAR
S/C 42.450 05.07.2001  
310   PILANI-CHANGOTHI
S/C 9.176 21.07.2001  
311  LAKHERI-ITAWA
S/C 23.300 05.11.2001  
312  BANSUR-THANAGAZI
S/C 34.890 30.01.2002  
313  JHUNJHUNU-KUMAWAS S/C
15.887 27.03.3002  
314  TPS TO 220KV TINWARI
S/C 12.489 31.07.2001  
315  KHINVSAR-SOILA
S/C 20.122 31.07.2001  
316  CHHOTI SADRI-BARI SADRI
S/C 22.769 15.08.2001  
317  BILARA-PIPARCITY
S/C 32.234 28.11.2001  
318  LILO -Banswara-Mahi II FOR BAGIDORA
D/C 3.000 30.11.2001  
319  DHORIMANNA-SAWA
S/C 30.834 13.03.2002  
320 LILO -Deogarh-Kharchi FOR JOJHAWAR D/C 25.768
26.03.2002  
321 LILO -Barmer-jaisalmer FOR SHEO
D/C 5.740 24.04.2002  
322  I/C OF 132 KV SRSI/BAGRU LINE
S/C 1.694 14.08.2002  
323  LILO- Makrana-Bagot For Bidiyad
S/C 32.680 31.08.2002  
324  MOLASAR/DEEDWANA S/C
21.787 31.10.2002  
325  NAPASAR/BADNU
S/C 25.491 27.11.2002  
326  SAWAIMADHOPUR/UNIARA/NAINWA
S/C 55.592 28.11.2002  
327  SIRSI-BHANKROTA- BAGRU
D/C 3.234 31.12.2002  
328  UDHYOG VIHAR/SADULSHAR
S/C 22.494 17.01.2003  
329  DHOD/KHOOD
S/C 11.356 20.01.2003  
330  RAJGARH/TARANAGAR
S/C 32.000 21.01.2003  
331  PHULERA/JOBNER S/C
19.213 28.01.2003  
332  JHUNJHUNU/MANDAWA
S/C 21.119 29.01.2003  
333  LILO -Pindwara-Sukher for GOGUNDA
D/C 1.364 31.01.2003  
334  KUCHERA/SANJOO
S/C 22.969 13.02.2003  
335  SAWA/KAPASAN
S/C 33.820 14.02.2003  
336  LILO -Bikaner-Nokhar For DESNOKH
D/C 9.210 17.03.2003  
337  LILO -Bikaner-Bajju FOR KOLAYAT
D/C 4.590 24.03.2003  
338  MARKHI - AJEETGARH S/C
10.062 30.03.2003  
339  LILO -Laxmangarh-Nadbai FOR KHERLI
D/C 10.730 31.03.2003  
340  BIDASAR - BAMBOO
S/C 24.477 31.03.2003  
341  BAMBOO - TEHENDESAR
S/C 12.010 31.03.2003  
342  LILO -Debari-Bhinder FOR BHATEWAR
D/C 3.322 31.03.2003  
343 LILO Tinwari-Dechu FOR BALESAR
D/C 52.836 08.05.2003  
344  BALOTRA-SAMDARI S/C
35.505 29.03.2004  
345  BALOTRA-SINDHARI
S/C 42.533 23.02.2004  
346  BHAWANI MANDI-HEMDA
S/C 24.170 21.02.2004  
347  BHINMAL-POONASA
S/C 22.576 11.02.2004  
348  I/C BHOPALGARH
D/C 10.670 20.11.2003  
349  LILO Jhunjhunu-Churu FOR BISSAU
D/C 3.600 30.07.2003  
350  DAHRA-ANTA-BARAN
S/C 50.021 24.07.2003  
351  LILO Bhinmal- Sayla FOR DASPAN
D/C 11.054 19.12.2003  
352  DHOLPUR-RAJAKHERA
S/C 38.860 28.11.2003  
353  JHUNJHUNU-MANDRELLA
S/C 24.094 22.05.2003  
354  KISHANGARHBAS-TIZARA
S/C 17.448 24.01.2004  
355  LILO Kankroli-Amet FOR MOKHAMPURA
D/C 0.902 09.04.2003  
356  PADAMPUR-SRIKARANPUR
S/C 22.242 17.07.2003  
357  I/C PALI
D/C 6.224 02.04.2003  
358  LILO -Dechu-P.S.V FOR PHALODI
D/C 1.780 22.01.2004  
359  LILO Madri-Sukher FOR PRATAPNAGAR
D/C 1.800 31.03.2004  
360  LILO Chittorgarh-Nimbahera FOR SENTHI
D/C 1.962 27.03.2004  
361  TONK-TODARAISINGH
S/C 34.666 31.03.2004  
362  LILO -Hindaun-Mandawar FOR TODABHIM
D/C 15.624 27.05.2003  
363  WEIR-BHUSAWAR
S/C 11.445 25.08.2003  
364 LILO -Jaisalmer-Pokran FOR CHANDAN
D/C 3.394 01.06.2004  
365  DAUSA-TOONGA
S/C 24.046 10.12.2004  
366  LILO Bhilwara-Kharchi FOR DEOGARH
S/C 5.031 29.03.2005  
367  LILO FOR GUDAMALANI
D/C 5.892 06.12.2004  
368  LILO Alwar-Rajgarh FOR MALAKHERA
D/C 1.340 08.07.2004  
369  TINWARI-OSIAN
S/C 22.298 22.12.2004  
370  LILO FOR BHADRONA
D/C 20.950 24.03.2005  
371  I/C SUJANGARH
D/C 1.025 21.06.2004  
372 BALOTRA-SAMDARI(D/C PORTION) D/C 2.324 16.04.2004  
373 HEERAPURA-VKIA (EXITING LINE) S/C 0.913 2002-03  
374 LILO -Sirohi-Jalore For BAGRA D/C 6.920 31.08.2005  
375 LILO BIDIYAD OFF D/C 1.248 31.08.2002  
376 LILO -Bikaner-Kolayat For BHINASAR S/C 2.320 31.03.2006  
377 CHITAWA-LOSAL S/C 20.507 26.11.2005  
378 LILO Bhilwara-Kharchi FOR DEOGARH D/C 5.031 21.05.2005  
379  GOGUNDA-MANASIWAKAL
S/C 31.112 20.05.2005  
380 KAWAI-CHHIPABARODA S/C 20.565 26.10.2005  
381 LILO Jhalawar-Sangod FOR KHANPUR D/C 27.570 31.03.2006  
382 KHINVSAR-BHOMIYAJI KA MOD(HESABA) S/C 21.707 30.12.2005  
383 KHINVSAR-BHOMIYAJI KA MOD(HESABA) D/C 0.560 30.12.2005  
384 PADAMPUR-RAISINGHNAGAR S/C 26.234 24.10.2005  
385 RANIWARA-SANKAD S/C 22.140 10.03.2006  
386 RATANGARH-MOMASAR S/C 33.865 31.03.2006  
387 SALASAR-KACHHAWA S/C 19.270 06.03.2006  
388 SHAHPURA-MANOHARPUR S/C 12.951 10.09.2005  
389 SUJANGARH-SALASAR D/C 44.550 27.02.2006  
390 TODABHIM-SIKANDRA S/C 27.879 31.03.2006  
391 LILO -Reengus-Danta FOR KHATUSHYAMJI D/C 1.214 25.01.2007  
392 JHALAWAR-BAKANI S/C 25.153 29.05.2006  
393 LILO -Dausa-Puranaghat FOR BASSI D/C 5.410 03.06.2006  
394 SANGANER-BALAWALA (DEPOSIT WORK OF PHED) S/C 4.431 03.06.2006  
395 LILO BARMER-SHEO FOR 220KV GSS BARMER D/C 20.226 01.11.2006  
396 SAYLA-JEEWANA S/C 20.064 16.11.2006  
397 JALORE-SAYLA D/C 76.964 22.01.2007  
398 LILO Sirohi-Bhinmal FOR RAMSEEN D/C 2.200 25.02.2007  
399 LILO Tinwari-Dechu FOR Chamu D/C 2.714 27.02.2007  
400 BARMER-MEHLOO S/C 37.705 28.02.2007  
401 RAYLA-SHAHPUR(BALANCE WORK) S/C 0.260 26.03.2007  
402 MERTAROAD-MERTACITY D/C 33.530 28.03.2007  
403 MERTAROAD-ROON S/C 20.609 28.03.2007  
404 DEPOSIT WORK OF M/S AMTEK AT 220KV GSS BHIWADI S/C 1.000 31.03.2007  
405 MANSIWAKAL-JHADOL D/C 13.660 30.03.2007  
406 SAYLA-PADROO S/C 25.138 31.03.2007  
407 SHIFTING OF BEAWAR-GULABPURA LINE FOR M/s SHREE CEMENT (DEPOSIT WORK) S/C 0.961 22.04.2007  
408 MODIFICATION OF SHUKHER-PINDWARA LINE FOR M/s BINANI CEMENT (DEPOSIT WORK) S/C 1.000 24.04.2007  
409 LILO SIWANA-JALORE FOR 220KVGSS JALORE D/C 18.628 25.05.2007  
410 KHUSHKHERA-M/s SHREE CEMENT (DEPOSIT WORK) S/C 2.635 19.06.2007  
411 LODHA-MORDI LINE (DEPOSIT WORK OF M/s RSWML, BANSWARA) S/C 12.741 02.07.2007  
412 LILO OF RATANGARH-BIKANER LINE FOR 220 kV GSS SRIDUNGARGARH D/C 1.846 11.07.2007  
413 RISHABDEO-RSWM RISHABDEO S/C 0.478 27.07.2007  
414 REENGUS-RSWM REENGUS (DEPOSIT WORK) S/C 2.222 18.08.2007  
415 LILO FOR KUNDAN D/C 3.844 27.08.2007  
416 LILO FOR MANDWA D/C 7.4 27.08.2007  
417 LILO FOR AJOLIYA KA KHERA D/C 17.876 19.09.2007  
418 SHAHJAHANPUR-MANDAN S/C 14.121 29.10.2007  
419 GULABPURA-RSWM GULABPURA (DEPOSIT WORK) S/C 1.6 19.11.2007  
420 HAMEERGARH-RSWM HAMEERGARH (DEPOSIT WORK) S/C 1.05 30.11.2007  
421 THADOLI-TODARAISINGH D/C 18.104 29.12.2007  
422 BHAWANIMANDI-KANWARI S/C 19.257 21.01.2008  
423 DUNI-THADOLI (LINE-I) S/C 30.992 19.02.2008  
424 LILO FOR RAMGARH D/C 16.494 19.03.2008  
425 Jalore-Sayla D/C 76.964 22.01.2008  
426 Kotputli-M/S Grasim Industries S/C 5.084 22.04.2008  
427 Khushkhera -Honda Seil D/C 1.612 09.09.2008  
428 Govindgarh -Kaladera S/C 10.108 04.07.2008  
429 LILO of 132kV Sawaimadhopur-Sheopur line for Khandar D/C 25.934 05.07.2008  
430 Duni-Thadoli(Circuit II) S/C 30.357 10.07.2008  
431 LILO for Deoli-Manjhi D/C 3.568 30.07.2008  
432 Aklera-Manoharthana S/C 37.890 24.12.2008  
433 132kV GSS Khushkhera-M/S Nahar Ind. D/C 5.756 16.06.2008  
434 LILO of 132kV Behror-Shahjahnpur line for Neemrana D/C 2.552 03.10.2008  
435 Karauli-Sapotra S/C 35.458 02.03.2009  
436 LILO of 132kV Modak-Jhalawar line for 132kV GSS Maylaramganjmandi D/C 8.990 10.03.2009  
437 Madri-Reliance Chemotex S/C 2.250 16.05.2008  
438 LILO of 132kV Ajmer-Kishangarh for 220kV Kishangarh D/C 10.122 28.11.2008  
439 LILO of RPS-Mandalgarh line for Beegod D/C 1.680 26.01.2009  
440 LILO of 132kV Kishangarh-Malpura line for 132kV GSS Silora D/C 13.152 24.03.2009  
441 Pali-Sojat city S/C 31.945 10.06.2008  
442 Phalodi-Aau S/C 51.573 14.07.2008  
443 Phalodi-Lohawat S/C 26.900 19.07.2008  
444 D/C portion, common to both Phalodi-Aau & Phalodi-Lohawat Lone D/C 13.794

14.07.2008/

19.07.2008

 
445 Dechu-Kalau S/C 26.912 23.10.2008  
446 Lohawat-Matora S/C 27.895 24.11.2008  
447 Sheo-Undoo S/C 47.980 01.12.2008  
448 Gharsana-Khajuwala S/C 61.854 26.09.2008  
449 Sujangarh-Parewara S/C 37.210 14.02.2009  
450 LILo of 132kV Bhadra-Sadulpur line for 220kV GSS Bhadra D/C 4.200 30.03.2009  
451 LILO of 132KV Alwar-Bharatpur line for
132KV GSS Kumher
D/C 6.484 26.07.2009  
452 LILO 132KV Anta-Baran line for 220KV GSS Barna
D/C 1.756 10.07.2009  
453 132KV S/C Jhalawar-Kanwari S/C 20.52 26.07.2009  
454 132KV line from Baran GSS to traction
substation at Baran Railway Station
(Deposit work)
S/C 2.868 03.08.2009  
455 132KV Interconnecting line from 220KV GSS VKIA to 132KV GSS VKIA S/C 0.296 30.11.2009  
456 132KV Interconnecting line from 220KV GSS VKIA to existing 132KV
VKIA-Kukas line
S/C 0.682 04.12.2009  
457 132KV LILO of Sangod-Baran line for 220KV GSS Baran D/C 7.104 07.12.2009  
458 132 kV LILO of Kotputli-Shahpura line
for 132KV GSS Paota
D/C 0.96 07.02.2010  
459 132KV S/C Balawala-Phagi Line S/C 21.687 15.03.2010  
460 132KV S/C Sawamadhopur-Bhadoti line S/C 29.968 24.03.2010  
461 LILO of 132KV Bundi-Deoli line for
132KV GSS Hindoli
D/C 7.94 30.03.2010  
462 132KV LILO of K.G.Bas-Bhiwadi line for
220KV GSS Khushkhera
D/C 4.88 31.03.2010  
463 LILO of 132KV Kotputli-Neem ka thana
line for 132KV GSS Patan
D/C 4.156 22.04.2009  
464 LILO of 132KV Pratapnagar-Banswara
line for 132KV GSS Dalot
D/C 47.000 25.04.2009  
465 LILO of 132KV Sikar-Udaipurwati line
for 132KV GSS Piprali
D/C 6.78 24.05.2009  
466 LILO of 132KV Kishangarh-Phulera line
for 220 KV GSS Kishanghar
D/C 24.2 27.06.2009  
467 132KV S/C Nagaur-Jayal S/C 47.156 03.02.2010  
468 LILO of 132KV RPS-Beegod(ckt.-I) for
132KV GSS Bijoliya
D/C 28.668 31.03.2010  
469 132KV S/C Banswara-Paloda line S/C 35.458 31.03.2010  
470 LILO of 132KV Bikaner-Sridungargarh
line for 132KV GSS Dulchasar
D/C 18.944 22.05.2009  
471 132KV Sridungargarh-Badnu S/C 27.701 27.06.2009  
472 LILO for 132KV Jalore-Siwana line for
132KV GSS Mandalwala
D/C 3.222 31.08.2009  
473 LILO for 132KV Barmer-Gadra Road
Line for 220 KV GSS Barmer
D/C 15.498 29.11.2009  
474 LILO for 132KV Bhinmal-Gudamalani
line for 132KV GSS Bagora
D/C 12.986 06.12.2009  
475 132KV Rajiasar-Shree Cement
(Deposit work)
D/C 11.09 22.01.2010  
476 132KV S/C Badnu-Jasrasar D/C 29.699 27.02.2010  
477 132 kV Line from Kawaii GSS to traction Sub station at
Chabra Gugor Railway Station (deposit work)
S/C 15.951 07.04.2010  
478 132 kV LILO of Bagru - Bhankrota Line for 220 kV GSS Bagru D/C 7.256 04.05.2010  
479 LILO of Kotputli - Behror line for 132 kV GSS Keshwana D/C 3.746 18.06.2010  
480 LILO of Bhiwadi-Khushkhera line for 132kV GSS Chopankhi D/C 10.034 22.07.2010  
481 Interconnection of 132 kV Puranaghat - Sitapura line at 220 kV GSS IndiragandhiNagar D/C 0.404 30.10.2010  
482 132 kV S/C Phulera - Dudu Line S/C 21.948 17.11.2010  
483 132 kV S/C Jobner - M/s Shree Cement Line(Deposit work) S/C 6.314 15.11.2010  
484 132 kV S/C Behror - Jhakrana (Turnkey Line) S/C 15.486 06.12.2010  
485 132 kV S/C Kawai - Atru (Turnkey Line) S/C 11.53 14.12.2010  
486 132 kV S/C Duni - Deoli Line S/C 33.402 15.12.2010  
487 132 kV D/C LILO of Mandawar -Todabhim for 132 kV GSS Mahuwa
D/C 1.616 22.02.2011  
488 132 kV D/C LILO of S/C JamwaRamgarh- Rajgarh line for 132 kV GSS Andhi D/C 3.32 17.02.2011  
489 132 kV LILO of Heerapura - Hongonia for 132 kV GSS Champapura D/C 4.598 22.02.2011  
490 132 kV S/C Dholpur - Roopwas line (Turnkey)** S/C 45.297 16.03.2011  
491 132 kV D/C LILO of Bundi - Kota Line for 132 kV GSS Talera ** D/C 4.47 26.03.2011  
492 132 kV LILO of Kota - Modak line for 132 kV GSS Mandanatown ** D/C 9.542 27.03.2011  
493 132 kV S/C Rayla - M/s Sangam Industries (Deposit work)
S/C 6.251 10.04.2010  
494 132 kV LILO of Nibahera - Sawa line for 132 kV GSS Bhadesar D/C 29.22 26.04.2010  
495 132 kV LILO of Bhilwara - Rayla line for 132 kV GSS Danta D/C 9.156 06.06.2010  
496 132 kV S/C Kishangarh - Roopangarh Line S/C 22.426 10.06.2010  
497 132 kV LILO of Bhilwara - Pali line for 132 kV GSS Karera D/C 3.792 17.06.2010  
498 132 kV Banswara - Mahi Cement(Deposit work) S/C 19.31 27.06.2010  
499 132 kV Jhunjhunu-Bherunda kalan S/C 18.24 29.07.2010  
500 132 kV S/C Surajgarh - Dulaniya (Turnkey) (13.722 CKM Commissioned on 28.07.2010 & 0.448 CKM Commissioned on 28.01.2011) S/C 14.17 28.07.2010  
501 132 kV Sultana-Bherunda kalan
S/C 13.789 28.10.2010  
502 132 kV LILO of Khinwsar - Soyla line for 132 kV GSS Narwa D/C 23.062 07.12.2010  
503 132 kV S/C Salumber - Dhariyawad (Turnkey) S/C 68.784 20.12.2010  
504 132 kV S/C Neem Ka Thana - Binani Cement (deposit work) S/C 5.64 15.12.2010  
505 132kV LILO of Khetrinagar-Neem Ka Thana line at 132 kV GSS Babai D/C 2.384 19.01.2011  
506 132 kV S/C Ranoli - Khandela Mod ** S/C 25.001
24.03.2011
 
507 132 kV LILO of Laxmangarh - Fatehpur line for 132 kV GSS Antroli ** D/C 18.81 27.03.2011  
508 132 kV LILO for Sancore
D/C 6.636 28.04.2010  
509 132 KV S/C Sanchore - Galifa Line S/C 18.502 28.04.2010  
510 132 kV S/C Sridungargarh-Riri
S/C 16.855 24.06.2010  
511 132 kV LILO of Suratgarh-Anoopgarh Line for 132 kV GSS Srivijaynagar D/C 20.752 26.06.10  
512 132 kV Reodar - Badgaon
S/C 34.933 30.06.2010  
513 132 kV LILO of Pali - Falna line for 132 kV GSS Tagore Nagar D/C 1.246 15.08.2010  
514 132 KV LILO of Dhorimanna - Sawa line for 132 kV GSS Ranasar D/C 9.56 03.11.2010  
515 132 kV S/C Sawa- Sata line S/C
46.011
07.01.2011  
516 132 KV LILO of Jalore-Jeewana line for 132 kV GSS Sayla D/C 2.592 13.01.2011  
517 132 kV S/C Dechu - Sanwreej line **
S/C 24.71 14.03.2011  
518 132 KV LILO of Dechu-Pokhran line for 220 kV GSS Dechu **(Only one Ckt. Charged) S/C 1.105 28.03.2011  
519 132 kV S/C Sangaria - Biomass Plant(Deposit work) ** S/C 0.35 31.03.2011  
  Total 132 KV Lines
  13919.119
   
 