| S. NO. |
NAME OF THE SECTION |
NO. OF CIRCUITS |
TOTAL LENGTH (CIRCUIT KILOMETER) |
YEAR OF COMPLETION / ENERGISATION |
|
| 1 |
Hissar-Khetri |
S/C |
115.000 |
March,69 |
|
|
| 2 |
Khetri-Jaipur |
S/C |
144.000 |
July,69 |
|
|
| 3 |
RAPP-Debari |
S/C |
192.000 |
May,70 |
|
|
| 4 |
RAPP-Kota-Jaipur |
D/C |
468.000 |
Feb.71 |
|
|
| 5 |
Badarpur-Jaipur(Rajasthan Section) |
S/C |
161.810 |
22-11-75 |
|
|
| 6 |
Kota-Ujjain |
D/C |
112.000 |
20.8.77/2.1.88 |
|
|
| 7 |
RAPP-Kota(III CIRCUIT) |
S/C |
42.000 |
1/9/1977 |
|
|
| 8 |
Dadri-Khetri |
S/C |
70.910 |
23/12/77 |
|
|
| 9 |
Khetri-Jaipur |
S/C |
138.830 |
8/9/1979 |
|
|
| 10 |
Kota-Bhilwara |
D/C |
260.000 |
16/11/80 |
|
|
| 11 |
Khetri-Ratangarh |
S/C |
123.000 |
26/11/80 |
|
|
| 12 |
Bhilwara-Beawar |
S/C |
93.000 |
30/9/81 |
|
|
| 13 |
Inter Connection between 220 kV GSS Kota &
KTPS |
D/C |
1.500 |
16/10/81 |
|
|
| 14 |
Agra-Bharatpur |
S/C |
48.000 |
30/12/82 |
|
|
| 15 |
Bhilwara-Sirohi |
S/C |
199.690 |
23/3/83 |
|
|
| 16 |
Heerapura-Chomu-Reengus |
D/C |
136.400 |
30/12/83 |
|
|
| 17 |
Jodhpur-Bhilwara |
S/C |
195.450 |
7/3/1984 |
|
|
| 18 |
KTPS-Sakatpura |
S/C |
1.500 |
2/9/1983 |
|
|
| 19 |
Dadri-Khetri |
S/C |
77.180 |
2/3/1985 |
|
|
| 20 |
Bhilwara-Debari |
S/C |
141.360 |
26/3/85 |
|
|
| 21 |
Kota-Jaipur(IIIcircuit) |
D/C |
12.720 |
28/2/86 |
|
|
| 22 |
Kota-Jaipur(IIIcircuit) |
S/C |
183.920 |
28/2/86 |
|
|
| 23 |
Beawar-Ajmer |
S/C |
59.310 |
30/4/86 |
|
|
| 24 |
Reengus-Sikar-Ratangarh |
S/C |
138.640 |
16/2/87 |
|
|
| 25 |
Heerapura-Phulera-Ajmer |
S/C |
123.600 |
31/3/88 |
|
|
| 26 |
Kota-Anta |
S/C |
7.270 |
31/12/88 |
|
|
| 27 |
Kota-Anta |
D/C |
117.500 |
3/1/1990 |
|
|
| 28 |
Ratangarh-Suratgarh |
S/C |
167.900 |
31/3/90 |
|
|
| 29 |
Interconnection between KTPS & 220 kV GSS(III
Cir.) |
S/C |
0.670 |
23/11/90 |
|
|
| 30 |
Kota-Beawar |
D/C |
380.000 |
15/3/91 |
|
|
| 31 |
Khetri-Reengus |
S/C |
100.000 |
1/9/1990 |
|
|
| 32 |
Dausa- Alwar |
S/C |
95.130 |
31/3/92 |
|
|
| 33 |
Beawar-Jodhpur |
S/C |
139.310 |
6/11/1991 |
|
|
| 34 |
Debari-Banswara |
S/C |
150.000 |
18/1/92 |
|
|
| 35 |
LILO-Chittorgarh |
D/C |
2.000 |
1991-92 |
|
|
| 36 |
Barsinghsar-Bikaner |
S/C |
31.600 |
20/6/92 |
|
|
| 37 |
Dausa TO Bharatpur |
S/C |
133.306 |
5/12/92,23/10/92 |
|
|
| 38 |
LILO Anta -Jaipur Dausa Circuit I for SawaiMadhopur |
D/C |
15.688 |
26/1/93 |
|
|
| 39 |
Suratgarh GSS To TPS Suratgarh |
S/C |
25.130 |
31/3/93 |
|
|
| 40 |
LILO DC Dausa-Anta Line NO.2 |
D/C |
29.650 |
17.5.93 |
|
|
| 41 |
LILO of Kota-Ujjain for (Chandrapura-Morak) |
D/C |
22.290 |
16.10.93 |
|
|
| 42 |
Morak -Jhalawar |
S/C |
28.520 |
18.10.93 |
|
|
| 43 |
Alwar- Bhiwadi |
D/C |
164.480 |
29.1.94 & 9.2.94 |
|
|
| 44 |
Dausa-Hindaun |
S/C |
85.890 |
31.3.94 |
|
|
| 45 |
LILO Beawar-Jodhpur for Bilara |
D/C |
6.720 |
30.7.94 |
|
|
| 46 |
Suratgarh Grid Choki-Suratgarh Thermal |
S/C |
25.000 |
4.5.94 |
|
|
| 47 |
Beawar -Merta |
S/C |
73.410 |
16.12.95 |
|
|
| 48 |
Jodhpur-Balotra |
S/C |
110.380 |
15.6.95 |
|
|
| 49 |
IV & Vth I/C between Sakatpura-KTPS |
D/C |
1.300 |
29.9.95 |
|
|
| 50 |
LILO-Bhilwara-Sirohi I for Bali |
D/C |
2.880 |
22.3.96 |
|
|
| 51 |
Suratgarh -Hanumangarh |
S/C |
64.480 |
31.3.96 |
|
|
| 52 |
Merta-Nagaur |
S/C |
67.660 |
31.3.97 |
|
|
| 53 |
Bikaner-Ratangarh |
D/C |
255.610 |
9.11.96 |
|
|
| 54 |
LILO-Bhilwara-Sirohi II for Kankroli |
D/C |
4.840 |
31.3.97 |
|
|
| 55 |
Bhilwara-Kankroli- Sirohi |
S/C |
81.840 |
23.11.96 |
|
|
| 56 |
Sirohi-Bhinmal |
S/C |
60.939 |
31.3.97 |
|
|
| 57 |
LILO-Jaipur-Kukas for Alwar |
D/C |
36.780 |
31.3.98 |
|
|
| 58 |
LILO-JAIPUR- Kota line |
D/C |
6.060 |
31.3.98 |
|
|
| 59 |
Jodhpur-Tinwari |
S/C |
43.810 |
16.10.97 |
|
|
| 60 |
Sirohi-Balotra |
S/C |
131.540 |
31.3.98 |
|
|
| 61 |
Kankroli-Sirohi |
S/C |
144.530 |
31.1.98 |
|
|
| 62 |
Chittorgarh -Nimbhahera |
S/C |
42.160 |
31.3.98 |
|
|
| 63 |
Bikaner -Nagaur |
S/C |
106.270 |
31.3.98 |
|
|
| 64 |
Bikaner -Nagaur |
D/C |
1.480 |
97-98 |
|
|
| 65 |
Bali-Pindawara |
S/C |
50.510 |
11.3.99 |
|
|
| 66 |
Alwar- Kotputali |
S/C |
82.400 |
10.2.2000 |
|
|
| 67 |
LILO 220 KV Kota-Anta Lines For Dahara GSS |
D/C |
16.020 |
31.5.99 |
|
|
| 68 |
LILO Khetri-Ratangarh for Jhunjhunu |
S/C |
1.145 |
19.05.2000 |
|
|
| 69 |
LILO Heerapura-Bassi (I) |
D/C |
2.480 |
24.09.2000 |
|
|
| 70 |
LILO Heerapura-Bassi (II) |
D/C |
3.338 |
24.09.2000 |
|
|
| 71 |
Sikar - Kuchaman Sec. I |
S/C |
32.779 |
30.03.2001 |
|
|
| 72 |
Sikar - Kuchaman Sec. II |
S/C |
29.735 |
30.03.2001 |
|
|
| 73 |
Suratgarh - Udhyog vihar (Sri Ganganager) |
S/C |
60.425 |
31.03.2001 |
|
|
| 74 |
Ratangarh-Suratgarh |
S/C |
157.858 |
15.10.2001 |
|
|
| 75 |
Reengus-Sikar Section |
D/C |
108.336 |
30.11.2001 |
|
|
| 76 |
LILO Ratangarh-Suratgarh lines for STPS |
D/C |
11.976 |
20.12.2001 |
|
|
| 77 |
Ratangarh-Laxmangarh |
D/C |
117.878 |
28.02.2002 |
|
|
| 78 |
Sikar-Laxmangarh |
D/C |
44.372 |
28.02.2002 |
|
|
| 79 |
Bharatpur-Dholpur (Single circuit string) |
D/C |
74.933 |
11.09.2002 |
|
|
| 80 |
LILO Anta-Dausa Lines for Sawaimadhopur |
D/C |
13.334 |
19.10.2002 |
|
|
| 81 |
LILO for Alwar-Bhiwadi to 400 kV GSS Bhiwadi |
D/C |
8.088 |
15.01.2003 |
|
|
| 82 |
Merta-Bhopalgarh |
S/C |
53.109 |
03.03.2003 |
|
|
| 83 |
Merta-Bhopalgarh |
D/C |
3.710 |
03.03.2004 |
|
|
| 84 |
LILO Bhilwara-Jodhpur Lines for Pali |
D/C |
18.774 |
31.03.2003 |
|
|
| 85 |
LILO Ramgarh-Falodi for AMARSAGAR(CHARGED ON 132KV) |
D/C |
16.070 |
03.07.2004 |
|
|
| 86 |
BASSI-KUKAS |
D/C |
68.096 |
31.03.2005 |
|
|
| 87 |
LILO JODHPUR-BEAWAR for Bilara |
D/C |
49.376 |
19.08.2004 |
|
|
| 88 |
LILO Sirohi-Balotra For Jalore |
D/C |
0.600 |
28.12.2004 |
|
|
| 89 |
RAMGARH-PHALODI(CHARGED ON 132KV) |
D/C |
214.618 |
28.06.2004 |
|
|
| 90 |
RATANGARH-SUJANGARH |
S/C |
48.076 |
23.02.2005 |
|
|
| 91 |
BALOTRA-BARMER |
S/C |
92.285 |
27.03.2006 |
|
|
| 92 |
BALOTRA-BARMER |
D/C |
15.490 |
27.03.2006 |
|
|
|
| 93 |
GIRAL-BARMER |
S/C |
32.235 |
31.03.2006 |
|
|
| 94 |
LILO JODHPUR-TINWARI For 400kV Jodhpur |
D/C |
43.550 |
01.06.2005 |
|
|
| 95 |
JODHPUR-TINWARI |
S/C |
29.147 |
21.02.2006 |
|
|
| 96 |
PHALODI-TINWARI |
S/C |
90.749 |
28.04.2005 |
|
|
| 97 |
PHULERA-MAKARANA |
S/C |
56.425 |
08.12.2005 |
|
|
| 98 |
PHULERA-MAKARANA |
D/C |
0.716 |
08.12.2005 |
|
|
| 99 |
RATANGARH-JHUNJHUNU |
D/C |
151.624 |
21.05.2005 |
|
|
| 100 |
JHUNJHUNU-KHETRI |
D/C |
97.462 |
21.05.2005 |
|
|
| 101 |
RATANGARH-SUJANGARH |
D/C |
6.931 |
JUNE,2005 |
|
|
| 102 |
STPS-BIKANER |
S/C |
161.053 |
30.06.2005 |
|
|
| 103 |
DEBARI-CHITTORGARH |
S/C |
0.890 |
16.04.2005 |
|
|
| 104 |
BHARATPUR-DHOLPUR |
D/C |
74.859 |
24.01.2007 |
|
|
| 105 |
LILO-I CKT BHARATPUR-DHOLPUR AT DHOLPUR(GTPS) |
D/C |
1.264 |
24.01.2007 |
|
|
| 106 |
BARMER-DHORIMANNA |
S/C |
71.686 |
27.03.2007 |
|
|
| 107 |
MADA-BARMER |
D/C |
257.600 |
22.04.2007 |
|
|
| 108 |
KHINWSAR-BHOPALGARH |
S/C |
35.993 |
30.04.2007 |
|
|
| 109 |
LILO OF 220 kV DAUSA-BHARATPUR LINE FOR MANDAWAR |
D/C |
15.684 |
29.06.2007 |
|
|
| 110 |
LILO OF 220 kV RATANGARH-BIKANER LINE FOR 220
kV GSS SRIDUNGARGARH |
D/C |
4.616 |
25.07.2007 |
|
|
| 111 |
BARSINGHSAR-NAGAUR |
S/C |
104.084 |
30.07.2007 |
|
|
| 112 |
REALIGNMENT WORK OF 220 kV D/C LILO TO SANGANER |
D/C |
1.67 |
12.12.2007 |
|
|
| 113 |
LILO BHILWARA-KANKROLI F0R KANKROLI |
D/C |
9.48 |
17.01.2008 |
|
|
| 114 |
LILO FOR DHUNI |
D/C |
3.81 |
20.01.2008 |
|
|
| 115 |
LILO of 220kV Heerapura-Kukas line at 220kV GSS
VKIA |
D/C |
1.974 |
09.08.2008 |
|
|
| 116 |
Bhiwadi-Neemarana |
S/C |
51.828 |
21.09.2008 |
|
|
| 117 |
LILO of 220kV Alwar-Bhiwadi line at 220kV GSS
Khushkhera |
D/C |
4.716 |
21.09.2008 |
|
|
| 118 |
LILO of 220kV Bhiwadi-Neemrana line at 220kV GSS
Khushkhera |
D/C |
7.616 |
21.09.2008 |
|
|
| 119 |
Opening of one circuit of Heerapura-Bassi line
and connecting to 220kV GSS Sanganer & Phulera |
S/C |
59.398 |
13.06.2008 |
|
|
| 120 |
LILO of 220kV Chhabra-Baran-Dahra line at 220kV
GSS Kawai |
D/C |
2.080 |
21.06.2008 |
|
|
| 121 |
LILO of 220kV Ajmer-Phulera line at 220kV GSS
Kishangarh |
D/C |
0.234 |
07.06.2008 |
|
|
| 122 |
Barsinghsar-Khinvsar |
S/C |
102.311 |
27.10.2008 |
|
|
|
123
|
LILO of 220kV Giral-Barmer CKT.I for Rajwest |
D/C |
5.448 |
09.07.2008 |
|
|
| 124 |
Dhorimanna-Bhinmal |
S/C |
92.483 |
05.01.2009 |
|
|
| 125 |
Rajwest-Barmer |
D/C |
27.448 |
CKT.I(16.03.2009)
CKT.II(20.03.2009)
|
|
|
| 126 |
220kV STPS Suratgarh-Bhadra |
S/C |
114.163 |
31.03.2009 |
|
|
| 127 |
LILO OF 220 KV Heerapura
Reengus line for 220KV
GSS Renwal |
D/C |
49.99 |
28.05.2009 |
|
|
| 128 |
220 kV S/C Kawaii-Baran |
S/C |
49.67 |
19.05.2009 |
|
|
| 129 |
220 kV S/C Chhabra-Kawaii |
S/C |
41.75 |
30.06.2009 |
|
|
| 130 |
220 KV S/C Baran-Dahra |
S/C |
46.178 |
30.06.2009 |
|
|
| 131 |
220KV D/C Hindaun(400KV
GSS)-Hindaun(220KV
GSS) |
D/C |
16.002 |
09.09.2009 |
|
|
| 132 |
220KV LILO of Duni-
Heerapura for 220KV GSS
Sez |
D/C |
15.126 |
25.11.2009 |
|
|
| 133 |
220KV S/C Kankaroli(PGCIL)-
Debari Line |
S/C |
63.000 |
06.07.2009 |
|
|
| 134 |
II nd ckt. Stag. of Debari -
Banswara line up to Salumber
(Charged on 132KV) |
S/C |
87.151 |
18.08.2009 |
|
|
| 135 |
LILO of 220KV Bhilwara-
Bali line for 400KV GSS
Bhilwara |
D/C |
5.592 |
19.08.2009 |
|
|
| 136 |
LILO of 220KV Bhilwara-Pali
line for 400KV GSS Bhilwara |
D/C |
9.650 |
19.08.2009 |
|
|
| 137 |
220KV LILO of debari-
Banswara line for 132KV
GSS Salumber |
D/C |
16.508 |
16.02.2010 |
|
|
| 138 |
220 kV S/C Kankaroli(PG)-
Kankroli(RVPN) |
S/C |
8.280 |
08.03.2010 |
|
|
| 139 |
LILO of 220kv Sikar-Kuchamn line for 220KV GSS
Dhod |
D/C |
5.996 |
24.03.2010 |
|
|
| 140 |
LILO of 220kv KTPS-
Beawar line for 220KV GSS
Gulabpura |
D/C |
12.980 |
18.03.2010 |
|
|
| 141 |
220 kV S/C Merta(400KV)-
Makrana-Kuchaman line |
S/C |
108.139 |
31.03.2010 |
|
|
| 142 |
220KV link line at STPS-
end for 400KV STPS- Bikaner
line |
S/C |
3.485 |
23.09.2010 |
|
|
| 143 |
220 kV S/C GIRAL-Barmer-
(Ckt.-II) |
S/C |
34.848 |
01.10.2009 |
|
|
| 144 |
220 kV S/C Balotra-Baytoo |
S/C |
47.504 |
14.10.2009 |
|
|
| 145 |
220 kV S/C GIRAL-Baytoo |
S/C |
55.723 |
26.11.2009 |
|
|
| 146 |
LILO of 220KV Bikaner-
Nagaur line for 400KV GSS
Bikaner |
D/C |
37.244 |
12.02.2010 |
|
|
| 147 |
220 kV D/C portion in
aproach span at 400KV
GSS Akal |
D/C |
11.75 |
31.03.2010 |
|
|
| 148 |
LILO of 220KV Amarsagar-
Barmer line for 400KV
GSS Akal (only one ckt. charged) |
D/C |
19.512 |
31.03.2010 |
|
| 149 |
LILO of 220 kV Bassi - Phulera line for 220 kV
GSS Bagru
|
D/C |
9.332 |
12.05.2010 |
|
| 150 |
Hindaun-Mandawar |
S/C |
47.678 |
07.07.2010 |
|
| 151 |
LILO of 220 kV D/C Bassi - Heerapura line for
220 kV GSS |
D/C |
18.218 |
12.02.2011 |
|
| 152 |
Indira gandhi nagar
220 kV D/C LILO of Badarpur - Alwar for 220 kV GSS MIA Alwar |
D/C |
5.38 |
08.02.2011 |
|
| 153 |
LILO of 220 kV Kota - Bhilwara line for 400 kV
GSS PGCIL Kota ** |
D/C |
3.62 |
09.03.2011 |
|
| 154 |
220 KV D/C Neemrana - Kotputli Line ** |
D/C |
87.734 |
31.03.2011 |
|
| 155 |
220 kV LILO of Hissar - Khetri line for 220 kV
GSS Chirawa
|
D/C |
38.014 |
27.11.2010 |
|
| 156 |
220 kV LILO of Chittorgarh-Nimbahera line for
220 kV GSS Sawa |
D/C |
4.98 |
05.01.2011 |
|
| 157 |
LILO of 220 kV Bikaner - Nagaur line for 220 kV
GSS Nokha
|
D/C |
6.03 |
14.07.2010 |
|
| 158 |
LILO OF 220 KV JODHPUR - BALOTARA LINE AT 220
KV GSS BORANADA I/A *
(one Ckt. Charged on 01.04.10 & 2nd Ckt charged on 28.07.10)
|
D/C |
0.11 |
28.07.2010 |
|
| 159 |
LILO of Amarsagar - Barmer line to 400 kV GSS AKAL *
(i) For Bhu- GIRAL (one Ckt. Charged on 11.07.10& 2nd Ckt charged
on 08.08.10)
(ii) For Mada - Barmer(one Ckt. Charged on 31.03.10& 2nd Ckt
charged on21.08.10)
|
D/C
D/C
|
38.55
19.512
|
08.08.2010
21.08.2010
|
|
| 160 |
220 kV Pindwara - J.K.Laxmi Cement(Deposit work)(to
be Charged on 132 kV) |
S/C |
20.024 |
17.12.2010 |
|
| 161 |
220 kV D/C LILO of Sirohi- Kankroli line for Bali
|
D/C |
2.844 |
09.02.2011 |
|
| 162 |
220 kV S/C Bhinmal - Sanchore Line |
S/C |
67.347 |
15.02.2011 |
|
| 163 |
LILO OF 220 KV BIKANER-SRIDOONGARGARH LINE AT
400 KV GSS BIKANER * |
D/C |
6.618 |
15.02.2011 |
|
| 164 |
220kV LILO of Sirohi - Bhinmal line for 400kV
GSS Bhinmal(PGCIL) ** |
D/C |
9.674 |
29.03.2011 |
|
| 165 |
220 kV S/C Dhorimanna - Sanchore **
|
S/C |
63.836 |
31.03.2011 |
|
| 166 |
220 kV S/C Barsinghsar - Phalodi ** |
S/C |
125.785 |
31.03.2011 |
|
| 167 |
220 KV D/C LINES ( 3 CKT OF 5 KM EACH) AT APPROACH SECTION OF 400
KV GSS AKAL(JAISALMER) **
(i)Gantry of Bay No. 18-19 to Ckt -I
(ii)Gantry of Bay No. 16-17 to Ckt -II
|
D/C
D/C
|
10.07
9.59
|
31.03.2011
31.03.2011
|
|
|
| |
TOTAL 220 KV LINES |
|
10546.905
|
|
|
|
|