| ACHIEVEMENTS
IN RESPECT OF EHV WORKS DURING 2010-11 |
| S.NO. |
Name of Scheme |
Line Length / Capacity (Ckt.Km./MVA) |
Date of Completion / Commissioning |
|
|
(A)
|
400 kV WORKS :-
|
|
|
|
| (a) |
400 kV Substations
|
|
|
|
| 1 |
Hindaun
|
315
|
07.07.2010
|
|
| 2 |
Akal(Jaisalmer) |
|
|
|
|
| |
Total :- |
945
|
|
|
| (b) |
400 kV lines |
|
|
|
| 1 |
400 kV S/C Chhabra - Hindaun
|
268.288
|
30.04.2010
|
|
| 2 |
D/C Portion at Chhabra &
Hindaun End
|
73.158
|
30.04.2010
|
|
| 3 |
400 kV S/C Dahra/Kota-Bhilwara
|
158.143
|
30.09.2010
|
|
| 4 |
400 kV D/C Portion at Bhilwara
end(approach Section)
|
28.910
|
30.09.2010
|
|
| 5 |
400 kV S/C Jaisalmer-Barmer
|
142.584
|
07.10.2010
|
|
| 6 |
400 kV D/C KTPS - PGCIL (Nanta)(Charged
on 220 kV)
|
13.096
|
21.02.2011
|
|
| 7 |
400 kV D/C Rajwest - Barmer **(one
ckt. Commissioned on 21.05.2010 & 2nd ckt. Commissioned
on 28.03.2011)
|
30.622
|
28.03.2011
|
| |
Total :- |
714.801
|
|
|
| (B) |
220 kV WORKS :- |
|
|
|
| (a) |
220 kV lines :- |
|
|
|
| 1 |
LILO of 220 kV Bassi - Phulera
line for 220 kV GSS Bagru |
9.332
|
12.05.2010
|
|
| 2 |
Hindaun-Mandawar
|
47.678
|
07.07.2010
|
|
| 3 |
LILO of 220 kV D/C Bassi - Heerapura
line for 220 kV GSS
Indira gandhi nagar
|
18.218
|
12.02.2011
|
|
| 4 |
220 kV D/C LILO of Badarpur -
Alwar for 220 kV GSS MIA Alwar
|
5.38
|
08.02.2011
|
|
| 5 |
LILO of 220 kV Kota - Bhilwara
line for 400 kV GSS PGCIL Kota ** |
3.62
|
09.03.2011
|
|
| 6 |
220 KV D/C Neemrana - Kotputli Line ** |
87.734
|
31.03.2011
|
|
| 7 |
220 kV LILO of Hissar - Khetri
line for 220 kV GSS Chirawa
|
38.014
|
27.11.2010
|
|
| 8 |
220 kV LILO of Chittorgarh-Nimbahera
line for 220 kV GSS Sawa |
4.98
|
05.01.2011
|
|
| 9 |
LILO of 220 kV Bikaner - Nagaur
line for 220 kV GSS Nokha |
6.03
|
14.07.2010
|
|
| 10 |
LILO OF 220 KV JODHPUR - BALOTARA
LINE AT 220 KV GSS BORANADA I/A *
(one Ckt. Charged on 01.04.10 & 2nd Ckt charged on 28.07.10)
|
0.11
|
28.07.2010
|
|
| 11 |
LILO of Amarsagar - Barmer line
to 400 kV GSS AKAL *
(i) For Bhu- GIRAL (one Ckt. Charged on 11.07.10& 2nd Ckt
charged on 08.08.10)
(ii) For Mada - Barmer(one Ckt. Charged on 31.03.10& 2nd
Ckt charged on21.08.10) |
38.55
19.512
|
08.08.2010
21.08.2010
|
|
| 12 |
220 kV Pindwara - J.K.Laxmi Cement(Deposit
work)
(to be Charged on 132 kV) |
20.024
|
17.12.2010
|
|
| 13 |
220 kV D/C LILO of Sirohi- Kankroli
line for Bali |
2.844
|
09.02.2011
|
|
| 14 |
220 kV S/C Bhinmal - Sanchore
Line |
67.347
|
15.02.2011
|
|
| 15 |
LILO OF 220 KV BIKANER-SRIDOONGARGARH
LINE AT 400 KV GSS BIKANER * |
6.618
|
15.02.2011
|
|
| 16 |
220kV LILO of Sirohi - Bhinmal
line for 400kV GSS Bhinmal(PGCIL) ** |
9.674
|
29.03.2011
|
|
| 17 |
220 kV S/C Dhorimanna - Sanchore
** |
63.836
|
31.03.2011
|
|
| 18 |
220 kV S/C Barsinghsar - Phalodi
** |
125.785
|
31.03.2011
|
|
| 19 |
220 KV D/C LINES ( 3 CKT OF 5
KM EACH) AT APPROACH SECTION OF 400 KV GSS AKAL(JAISALMER) **
(i)Gantry of Bay No. 18-19 to Ckt -I
(ii)Gantry of Bay No. 16-17 to Ckt -II |
10.07
9.59
|
31.03.2011
31.03.2011
|
|
|
|
|
|
| |
Total :- |
594.946
|
|
|
| (b) |
220 kV Susbtations |
|
|
|
| 1 |
SEZ,Mahindra
|
100
|
01.04.2010
|
|
| 2 |
Bagru I/A
|
100
|
15.05.2010
|
|
| 3 |
Indira Gandhi Ngr
|
200
|
25.02.2011
|
|
| 4 |
MIA Alwar
|
100
|
08.02.2011
|
|
|
| 5 |
Chirawa
|
100
|
27.11.2010
|
|
| 6 |
Sawa
|
100
|
28.03.2011
|
|
| 7 |
Boranada I/A
|
100
|
01.04.2010
|
|
|
| 8 |
Nokha
|
100
|
18.10.2010
|
|
| |
Total :- |
900
|
|
|
| (C) |
132 kV WORKS :- |
|
|
|
| (a) |
132 kV lines :- |
|
|
|
| 1 |
132 kV Line from Kawaii GSS to
traction Sub station at
Chabra Gugor Railway Station (deposit work) |
15.951
|
07.04.2010
|
|
| 2 |
132 kV LILO of Bagru - Bhankrota
Line for 220 kV GSS Bagru |
7.256
|
04.05.2010
|
|
| 3 |
LILO of Kotputli - Behror line
for 132 kV GSS Keshwana |
3.746
|
18.06.2010
|
|
| 4 |
LILO of Bhiwadi-Khushkhera line
for 132kV GSS Chopankhi |
10.034
|
22.07.2010
|
|
| 5 |
Interconnection of 132 kV Puranaghat
- Sitapura line at
220 kV GSS IndiragandhiNagar |
0.404
|
30.10.2010
|
|
| 6 |
132 kV S/C Phulera - Dudu Line
|
21.948
|
17.11.2010
|
|
| 7 |
132 kV S/C Jobner - M/s Shree
Cement Line(Deposit work) |
6.314
|
15.11.2010
|
|
| 8 |
132 kV S/C Behror - Jhakrana
(Turnkey Line) |
15.486
|
06.12.2010
|
|
| 9 |
132 kV S/C Kawai - Atru (Turnkey
Line) |
11.53
|
14.12.2010
|
|
| 10 |
132 kV S/C Duni - Deoli Line
|
33.402
|
15.12.2010
|
|
| 11 |
132 kV D/C LILO of Mandawar -Todabhim
for 132 kV GSS Mahuwa |
1.616
|
22.02.2011
|
|
| 12 |
132 kV D/C LILO of S/C JamwaRamgarh-
Rajgarh line for 132 kV
GSS Andhi |
3.32
|
17.02.2011
|
|
| 13 |
132 kV LILO of Heerapura - Hongonia
for 132 kV GSS Champapura |
4.598
|
22.02.2011
|
|
| 14 |
132 kV S/C Dholpur - Roopwas
line (Turnkey)** |
45.297
|
16.03.2011
|
|
| 15 |
132 kV D/C LILO of Bundi - Kota
Line for 132 kV GSS Talera ** |
4.47
|
26.03.2011
|
| 16 |
132 kV LILO of Kota - Modak line
for 132 kV GSS Mandanatown ** |
9.542
|
27.03.2011
|
|
| 17 |
132 kV S/C Rayla - M/s Sangam
Industries (Deposit work) |
6.251
|
10.04.2010
|
|
| 18 |
132 kV LILO of Nibahera - Sawa
line for 132 kV GSS Bhadesar |
29.22
|
26.04.2010
|
|
| 19 |
132 kV LILO of Bhilwara - Rayla
line for 132 kV GSS Danta |
9.156
|
06.06.2010
|
|
| 20 |
132 kV S/C Kishangarh - Roopangarh
Line |
22.426
|
10.06.2010
|
|
| 21 |
132 kV LILO of Bhilwara - Pali
line for 132 kV GSS Karera |
3.792
|
17.06.2010
|
|
| 22 |
132 kV Banswara - Mahi Cement(Deposit
work)
|
19.31
|
27.06.2010
|
|
| 23 |
132 kV Jhunjhunu-Bherunda kalan
|
18.24
|
29.07.2010
|
|
| 24 |
132 kV S/C Surajgarh - Dulaniya
(Turnkey)
(13.722 CKM Commissioned on 28.07.2010 & 0.448 CKM Commissioned
on 28.01.2011) |
14.17
|
28.07.2010
|
|
| 25 |
132 kV Sultana-Bherunda kalan
|
13.789
|
28.10.2010
|
|
|
| 26 |
132 kV LILO of Khinwsar - Soyla
line for 132 kV GSS Narwa |
23.062
|
07.12.2010
|
|
| 27 |
132 kV S/C Salumber - Dhariyawad
(Turnkey) |
68.784
|
20.12.2010
|
|
| 28 |
132 kV S/C Neem Ka Thana - Binani
Cement (deposit work) |
5.64
|
15.12.2010
|
|
| 29 |
132kV LILO of Khetrinagar-Neem
Ka Thana line at 132 kV GSS Babai |
2.384
|
19.01.2011
|
|
| 30 |
132 kV S/C Ranoli - Khandela
Mod ** |
25.001
|
24.03.2011
|
|
| 31 |
132 kV LILO of Laxmangarh -
Fatehpur line for 132 kV GSS Antroli ** |
18.81
|
27.03.2011
|
|
| 32 |
132 kV LILO for Sancore |
6.636
|
28.04.2010
|
|
| 33 |
132 KV S/C Sanchore - Galifa
Line |
18.502
|
28.04.2010
|
|
| 34 |
132 kV S/C Sridungargarh-Riri
|
16.855
|
24.06.2010
|
|
| 35 |
132 kV LILO of Suratgarh-Anoopgarh
Line for 132 kV GSS Srivijaynagar |
20.752
|
26.06.10
|
|
| 36 |
132 kV Reodar - Badgaon |
34.933
|
30.06.2010
|
|
| 37 |
132 kV LILO of Pali - Falna line
for 132 kV GSS Tagore Nagar |
1.246
|
15.08.2010
|
|
| 38 |
132 KV LILO of Dhorimanna -
Sawa line for 132 kV GSS Ranasar |
9.56
|
03.11.2010
|
|
| 39 |
132 kV S/C Sawa- Sata line |
46.011
|
07.01.2011
|
|
| 40 |
132 KV LILO of Jalore-Jeewana
line for 132 kV GSS Sayla |
2.592
|
13.01.2011
|
|
| 41 |
132 kV S/C Dechu - Sanwreej
line ** |
24.71
|
14.03.2011
|
|
| 42 |
132 KV LILO of Dechu-Pokhran
line for 220 kV GSS Dechu **
(Only one Ckt. Charged) |
1.105
|
28.03.2011
|
|
| 43 |
132 kV S/C Sangaria - Biomass
Plant(Deposit work) ** |
0.35
|
31.03.2011
|
|
|
|
| |
Total: |
658.201
|
|
|
| |
132 kV Susbtations |
|
|
|
| 1 |
Chopankhi
|
20/25
|
22.07.2010
|
|
| 2 |
Phagi |
20/25
|
05.07.2010
|
|
| 3 |
Jhakarana |
20/25
|
08.12.2010
|
|
| 4 |
Keshwana
|
20/25
|
27.11.10
|
|
|
| 5 |
Atru
|
20/25
|
14.12.10
|
|
| 6 |
Dudu
|
20/25
|
26.03.11
|
|
| 7 |
Roopangarh
|
20/25
|
22.07.2010
|
|
| 8 |
Bherunda Kalan
|
20/25
|
31.07.2010
|
|
| 9 |
Babai
|
20/25
|
18.03.2011
|
|
|
| 10 |
Dhariyawad
|
20/25
|
27.12.10
|
|
| 11 |
Dulania
|
20/25
|
09.01.11
|
|
| 12 |
Karera
|
20/25
|
24.10.2010
|
|
| 13 |
Danta
|
20/25
|
10.09.2010
|
|
|
| 14 |
Narwa
|
20/25
|
18.01.2011
|
|
|
| 15 |
Galifa
|
20/25
|
08.05.2010
|
|
|
| 16 |
Badgaon
|
20/25
|
06.07.2010
|
|
|
| 17 |
Riri
|
20/25
|
24.06.2010
|
|
|
| 18 |
Tagore Nagar
|
20/25
|
25.08.2010
|
|
|
|
|
| 19 |
Sata
|
20/25
|
07.01.2011
|
|
|
| 20 |
Renasar
|
20/25
|
03.11.2010
|
|
|
| 21 |
Sanwreej
|
20/25
|
14.03.2011
|
|
|
| 22 |
Srivijaynagar
|
20/25
|
21.01.11
|
| |
Total: |
550
|
|
|
|
|
|
|